This is the information was Tran Van Luc – Director of Railway Project Management, Vietnam Railway Administration launched at the press briefing by the Department of Propaganda and Training Hanoi.

 

Perspective of elevated railway
As scheduled, starting March 1, 2015, the Cat Linh Urban Railway – Ha Dong (Ha Noi) will be commissioned. After that, it will be put into commercial operation from 1/6/2015.
Hanoi Urban Railway Project, Cat Linh – Ha Dong route officially started on 10/10/2011. However, until now, the work of site clearance (site clearance) continues to face many difficulties and obstacles.
Specifically, the site clearance in Phu Luong Ward (Ha Dong District); Trinh Luong cemetery extension to relocate Van Noi cemetery; handover landmark site clearance through the district of Dong Da, Thanh Xuan, underground high-voltage electricity line La Thanh – Lang.
At present, the project has constructed 252 piers (57% of volume), 73% of bored piles, 57% of piles and completed 50% of the work of processing weak ground and leveling the ground. At the same time, the contractors are implementing the construction of less than 5 stations including La Thanh, Ring Road 3, Thanh Xuan 3, Ha Dong and La Khe.
Mr. Luc also said that if in the coming time, this work will continue to be delayed, failing to meet the identified milestones, the project will not be able to complete the stated progress is very large .
As a result, the Railway Project Management Unit requests the Hanoi City People’s Committee to set up O & M Company immediately, or to assign a functional unit of the City to receive the sub-project of human resource training that is separated from the project. and recruiting staff in accordance with project standards to send training starts from June this year in accordance with the plan. In addition, TP directed drastically local, relevant units to actively implement, ensure the progress of handover of the site according to the plan has determined.